A fair question is whether "PRD to working MVP in one week" is a sales line. It is the plan we follow, and it works because the order of the work is fixed and the scope is cut hard before we start. This article walks through that plan day by day: what we build, what you see, what we need from you, and the things that make a week turn into two.
By "MVP" we mean a deployed application that real users can sign in to, with roles, the core workflow end to end, an admin panel, and tests. We do not mean a clickable prototype or a slide deck with screenshots.
What we need before day one
You do not need a polished PRD. A document, a set of mockups or a plain list of requirements is enough, as long as it answers a few questions. We usually settle these on a single call after the NDA is signed:
- Who the users are, and what each type of user is allowed to do. Two or three roles is typical for a first version.
- The one workflow that has to work end to end for the MVP to be worth showing. For a marketplace that might be "seller lists an item, buyer requests it, seller accepts".
- Which integrations are required in week one and which can be stubbed. Payments and sign-in with Google are common week-one items; ERP sync rarely is.
- Where it should run: our staging environment for the week, then your AWS or Google Cloud account, or your own servers.
- One person on your side who can answer questions within a few hours during the week.
The last item matters more than any of the others. Most of the decisions in a one-week build are small ("should a cancelled order still show in the seller list?"), and a quick answer keeps the build moving.
Day by day
The order is the important part. We build the backend first because the data model and the permission rules are the parts that are expensive to change later. The UI is built against a working API rather than against guesses.
- Day 1, backend from the PRD. We turn the requirements into a data model (entities, fields, relationships, which fields are required, which are private to a role), define the roles and what each can read and write, and generate the APIs. By the end of the day there is a staging link with a working backend, sign-in, and an API you can call.
- Day 2, core workflow and admin panel. We implement the main workflow on top of the API, including state changes and the rules around them (who can approve, what happens on cancel). The admin panel comes up the same day so your team can see and edit records without code.
- Day 3, customer-facing UI. Screens follow your mockups if you have them, or a clean default layout if you do not. Every screen talks to the real API with real permission checks, so a user who should not see a record does not see it.
- Day 4, validation environment and tests. We load realistic mock data (enough users, records and edge cases to make lists, filters and reports meaningful) into a separate validation environment and run the automated tests: API tests per role, workflow tests, and browser tests for the main paths.
- Day 5, fixes, deployment and demo. We fix what the tests and your review found, deploy, and walk you through the build. You leave the demo with the staging link, test report and a short usage guide.
| Day | What you see |
|---|---|
| 1 | Staging link, sign-in, data model and API you can call; role list confirmed |
| 2 | Main workflow working through the API; admin panel with real records |
| 3 | Customer-facing screens on the real backend, per role |
| 4 | Validation environment with mock data; first test report |
| 5 | Demo of the deployed MVP; test report, usage guide, source code access |
Why the backend comes first
When a UI is built first, the data model gets shaped by whatever the screens needed that week, and permissions get bolted on at the end as checks in the frontend. That is the most common reason MVPs have to be rewritten before a real launch: the second customer, the second role or the first security review exposes that the rules were never enforced on the server.
Starting with the model and the roles means every later step inherits them. The API refuses a request from a role that should not make it, regardless of what the UI shows. Field-level rules (for example, a buyer cannot see a seller's cost price) live in one place. When you add a screen in month three, it cannot accidentally expose data, because the backend never returns it.
What "working backend within one business day" actually includes
Concretely: persistent storage with the schema applied, authentication, role-based access on every endpoint, create/read/update/delete for each entity with validation, search and filtering on the fields the PRD says users will filter by, and an audit trail of writes. It does not yet include the business rules of the workflow; those come on day two.
In scope and out of scope for week one
A one-week MVP is a deliberate cut. We agree the cut in writing before day one so that nobody is surprised on day five.
Usually in
- Sign-in (email and password, plus Google or Microsoft sign-in if needed), password reset, and two or three roles.
- The core workflow end to end, with its states and notifications by email.
- An admin panel for managing users and records.
- One payment flow, if the product charges money, using a standard provider checkout.
- Basic reporting: counts and lists the PRD asks for, exportable to CSV.
- Deployment to staging and, if you are ready, to your cloud account.
Usually out (planned for week two onwards)
- Two-way sync with existing systems such as an ERP or CRM. We can read from them in week one; writing back needs more testing.
- Native mobile apps. The week-one web app is responsive and the API is ready for a mobile client.
- Complex pricing, tax rules across many regions, or custom billing logic.
- AI features beyond a single well-defined step. An agent that takes actions needs its own permissions and evaluation work.
- Multi-tenant onboarding, custom domains per customer and per-tenant SSO, unless the product is a multi-tenant SaaS from day one, in which case we scope that explicitly.
What makes a week slip
When a one-week build runs long, it is usually one of the following. None of them are unusual, and most can be avoided by naming them on the first call.
- Late answers. A question that waits two days for a reply costs two days, because later work depends on it.
- Scope that arrives mid-week. A new role or a new workflow on day three usually means revisiting the data model. We log it and plan it for week two rather than absorb it silently.
- Third-party access. API keys, sandbox accounts and test credentials for payment providers or existing systems often take days to arrive. We ask for them before day one.
- Undecided business rules. "We will figure out refunds later" is fine, but then refunds are out of week one.
- Production infrastructure that is not ready. If your cloud account, domain or DNS is not set up, we deploy to staging and move to production once access is in place.
If something will not fit, we say so on the day we find out, with the options: cut it, stub it, or move the demo. We do not hide a slip until day five.
What you get at the end of the week
At the demo you get the deployed application, access to the full source code (frontend and backend), the admin panel, the test suite and its report, the validation environment with mock data, a usage guide for each role, and the deployment scripts. The validation environment stays available, so you can run your own checks with realistic data before inviting real users.
Week two is usually for running the MVP past a handful of real users or investors and coming back with a list. Because the model, roles and tests are already in place, that list can turn into changes measured in days, not a rebuild.
Working with us
Our MVP Solutions engagement follows the plan above: a fixed scope agreed up front, a staging link on day one, and a demo at the end of the week. If you have a PRD, mockups or a list of requirements, send them over under NDA and we will tell you what fits in week one and what does not.